The Docks
The main elements of the West India Docks that were
constructed between 1800 and 1806 were the Import and
Export Docks, and the Blackwall and Limehouse basins,
linked to each other and to the Thames by six locks.
These features enclosed a total area of 62 acres of water.
Some indication of the relative scale of the works can be
gauged from the fact that in 1800 there were 78 acres of
wet dock and basin accommodation in the whole of
England, and that the wet docks at Liverpool, which
contained a larger area than those at any other British
port, covered only 28 acres. (ref. 196)
The principal addition to the West India complex was
the City Canal, acquired in 1829 to be the South Dock,
and reconstructed and enlarged in 1866–70. A small
Junction Dock was added in 1853–5 and a dry dock in
1876–8, but the system was not otherwise upgraded
until the Blackwall entrance lock was rebuilt in 1892–5.
Broadly, the docks were well suited to shipping throughout the early nineteenth century, but became obsolescent
in the late nineteenth century. Following the changing
demands of shipping, further major improvements were
carried out in the early twentieth century, particularly in
the late 1920s, when passages were added to link the
Import, Export and South Docks (Plate 45b).
Import Dock
The Import Dock is the northernmost rectangular wet
dock across the Isle of Dogs. The hub of the original
dock system, it was built in 1800–2 for the unloading of
West India shipping. It originally measured 2,600ft by
510ft and impounded 30 acres of water to a depth of
23ft. At the time of its construction it was by far the
biggest dock ever built. (ref. 197)
Ralph Walker's plans for the West India Docks prepared in late 1799 included a 'great Dock for unloading
Inwards' of 2,508ft by 478ft to accommodate up to 300
ships at a time (fig. 90b). Walker estimated the cost of
the dock and two entrance basins at £258,345. The final
plans for the dock were settled by William Jessop with
Walker in early 1800. Excavation contracts, for the Import
Dock and Blackwall Basin together, were given in four
lots of varying sizes, to John Holmes and William Bough
of Poplar, John Clark and Thomas Thatcher from Wiltshire, Samuel Jones, and Richard Minton, on behalf of
Bolton & Pixton. The digging started on 3 February
1800. Hundreds of men gradually shaped the great cavity,
but only Holmes & Bough were able to progress at a rate
that the dock company found satisfactory. Much of the
spoil was used to build up ground level from about 6ft
below high water (Trinity High Water) to quay level,
about 6ft above high water. The deeper parts of the
excavation were carried out by Holmes & Bough in 1801,
with the aid of a pumping steam-engine (see page 326). (ref. 198)
Preparations for the building of the brick walls which
line the dock began in late 1800. William Adam and
Daniel and Alexander Robertson contracted to use excavated clay to make 24 million bricks and Jessop ordered
6,000 tons of Dorking limestone for the mortar. The
Mylnes of Dundee supplied gritstone, cheaper than
granite, for the copings. Jessop's specification for the
walls was approved in January 1801, and Adam and the
Robertsons undertook to build them. (ref. 199) The first brick
was laid on 16 June 1801 and the walls went up with
extraordinary speed. By September up to 100 bricklayers
had laid all 2,600ft of the south wall to a height of 13ft
9in. Bricklaying continued at a rate of about one million
bricks each week. The supply of bricks failed to keep up
with this pace, and so some warehouse bricks were
appropriated, and other bricks had to be bought (see
page 255). (ref. 200)
The Import Dock was fully excavated by the end of
1801 (Plate 46a,b). Its walls were completed after the
winter break, but the coping was still unfinished when
water was introduced into the dock on 23 August 1802. (ref. 201)
The final cost of the Import Dock and two entrance
basins was £309,894; the problems of brick supply may
have been the principal factor behind the increase in
costs over the estimate made in 1799. (ref. 202)
The 1801–2 Import Dock walls survive, largely behind
and below later alterations (figs 96a, 107). The upper
parts of the west wall and the east end of the south wall
remain exposed. The walls are of a type first used by
Jessop in Dublin and Bristol in 1792–6, and widely
adopted in later dock works. They are of brick, 28–
29ft high, with a curved, or 'banana', section, both for
structural stability and to suit the shape of ships' hulls.
They are 6ft thick and backed by 3ft-thick counterforts,
or buttresses, at 10ft centres, to help prevent slippage.
The counterforts are bound to the main walling by
flattened iron hoops, the earliest known example of such
reinforced brickwork. The foundations were not piled,
because the gravel bed was considered, and has proved,
sufficiently stable. Clay puddle backed the walls and
covered the dock floor, to prevent water escaping through
the gravel. (ref. 203) In the mid-nineteenth century the
'inefficient' gritstone copings were replaced by Aberdeen
granite, and latticed timber fenders that had protected
the upper portions of the walls from contact with shipping
were removed. (ref. 204)
The Import Dock remained one of the roomiest docks
in the Port throughout the nineteenth century, yet from
mid-century its usefulness gradually declined, as no major
improvements were made for 90 years. The curved walls
prevented steamships of deep draught from mooring
alongside, and the dock fell into disuse in the late
nineteenth century. Better use of the Import Dock was
an early priority of the London and India Docks Joint
Committee, and in 1892 improvement of the north quay,
with timber wharfing projecting into the dock, was proposed, in conjunction with the rebuilding of the Blackwall
locks and the introduction of an impounding system to
increase the depth of water (see pages 269 and 326). (ref. 205)
H. F. Donaldson prepared 'ingenious' plans for an open, or
'false', quay, 20ft wide, to run 2,450ft along the north
side of the dock. This was built by John Price of
Westminster in 1894–5 and cost £17,779. It consisted of
492 creosoted pitch-pine piles (cheaper than iron), and
an asphalt-paved concrete floor on rolled-steel girders
and joists linked by wrought-iron arch plates (Plates 50c,
51a). (ref. 206) The 'false' quay was straight-sided, increasing
the depth of water alongside from 16ft to 23ft 6in. It
allowed dredging up to its edge, to further deepen the
dock without undermining the walls, and created space
for travelling quay cranes and transit handling. The
Import Dock was given a new lease of life, with 15 berths
for large steamers. The water depth was increased by
18in. when the impounding system came into operation
and dredging further increased the depth to 28ft. (ref. 207)
The Import Dock east quay was similarly improved in
1897–8. This 'false' quay, 365ft by 20ft, was built by
John Aird & Sons for £4,708, with steel girders, joists
and arch plates supplied by the Blaenavon Company. (ref. 208)
This structure survives, albeit in a damaged condition.
In 1900–1 the west quay was equipped with a 'false'
quay, 380ft by 19ft 6in., of similar construction, built
with direct labour for £4,562. It was removed in 1964. (ref. 209)
The north quay was rebuilt again in 1912–15 as part
of the PLA's first programme of improvements. Frederick
Palmer replaced the 1890s structure with a Hennebique
reinforced-concrete 'false' quay, 55ft 6in. wide and 2,456ft
long, in part to support new transit sheds (Plate 49c; fig.
107). It was built, with the sheds, by A. Jackaman &
Son, of Slough, with George Corderoy & Son as quantity
surveyors, for an estimated £97,350. The quay, which
survives, was novel in form, paralleled by contemporary
work at the London Docks. It has three rows of 5ftdiameter cylinders, each encasing three 14in.-square piles
and linked by precast braces. On the beam-and-slab
decking there are contemporary cast-iron bollards. (ref. 210) The
quay was strengthened by John Mowlem & Company in
1953 with additional 16in.-square concrete piles, two per
bay, and precast-concrete beams. (ref. 211)
A 580ft-long 'false' quay was built at the west end of
the Import Dock south quay in 1937 for the Canary
Wharf berth leased to Fruit Lines Ltd. It was designed
in Asa Binns's department and built by John Mowlem &
Company, following a type used at the Royal Albert Dock
in 1935. It was made 25ft wide to permit deepening of
the dock to 29ft and was founded on a single row of
columns of triple reinforced-concrete piles in precast
cylindrical shells. There were precast decking slabs and
granite-concrete coping. (ref. 212)
The south 'false' quay was extended eastwards in
1950–2. Ever-larger ships had to be accommodated in
the Import Dock, particularly as a third of the berths in
the Port had been immobilized by bomb damage. W. P.
Sheppard-Barron revived pre-war plans for two new
deep-water berths and John Mowlem & Company built
a 1,320ft length of 25ft-wide 'false' quay, similar to that
of 1937. The dock was deepened to 30ft 6in., then, in
1958, to 31ft 6in., by dredging and impounding. (ref. 213)
The Import Dock ceased to be used for shipping in
1976, and infilling was considered before the dock was
listed Grade I in 1983. (ref. 214) Stabilizing fill was deposited
against the 'banana' walls on the south side of the Import
Dock in 1986–7 prior to the construction of large decks
out over the dock for the Canary Wharf development. (ref. 215)
Export Dock
The Export Dock was built to the south of the Import
Dock in 1803–6 (fig. 90b). In 1799 Ralph Walker projected
a 'Dock for light Ships and loading outwards' of 23 acres,
with an estimated cost of £95,313, then, with Jessop, in
early 1800 settled the dock's size at 24 acres, 2,600ft by
400ft. (ref. 216) The Export Dock was given no further attention
until the Import Dock was open. Jessop prepared detailed
plans in 1803, fixing the water depth at 23ft 3in., and
Thomas Morris was taken on in December 1803 to
superintend the building of the dock, under Jessop until
late 1804. (ref. 217)
John Dyson, who was then working at the City Canal,
started the excavations in late 1803. Extra pumping
capacity was arranged by renting the Corporation's City
Canal steam engine. (ref. 218) Dyson fell behind his schedule
and, in April 1804, the dock company gave the main
excavation contract to Webb, Richards & Halse, but they
were discharged in July after the partners had fallen out,
Webb having run off with their money. The contract was
then taken up by William Bough and John Hughes, who
introduced a steam engine for 'hauling upwards of 2000
tons of gravel daily, upon an inclined plane 40ft in
height'. Excavation of the dock was completed in mid1805. (ref. 219)

Figure 96:
(opposite). West India Docks, dock- and lock-wall sections
a. Import Dock, 1801–2
b. Blackwall Entrance Lock, 1800–2
c. Junction Dock, 1853–5
d. South Dock, 1866–70
e. South Dock East Entrance Lock, as rebuilt 1869–70
f. West India Dock Graving Dock, 1876–8
g. Blackwall Entrance Lock, 1893–4
h. Poplar Dock Entrance Lock/Passage, 1850–1, as widened 1898–9
i. Bellmouth Passage, 1926–8
j. South Dock East Entrance Lock, 1927–9
The Export Dock walls, including the inner locks,
required 21 million bricks, many of which were made on
site by Fentiman & Company, and the remainder were
supplied by the Trimmers and others. (ref. 220) The Mylnes
again supplied Dundee gritstone for copings. The brickwork was carried out by Aslat, Collins, Gill & Steward,
the masonry by Thomas and William Crawford. The
bricklaying was under way by April 1804 and was completed by early 1806. The Export Dock walls follow the
Import Dock walls closely in materials, form
and dimensions, differing slightly at the toes (Plate
51b). (ref. 221)
The Export Dock opened to shipping on 12 July 1806
with a ceremony attended by thousands of onlookers. It
had cost £197,738 to build. (ref. 222) Initially, it was heavily
used, as all shipping bound for the West Indies was
required to load at its north quay. With the loss of the
monopoly on West India trade in 1823 the dock came to
be used for other purposes. In 1825 four 9ft-wide granite
slips for landing floated timber were built into its quays
near the south-east corner. These slips were removed in
1874, but timber rafting in the dock went on into the
1930s. (ref. 223)
Timber jetties were put up in the Export Dock, four
in 1846 and ten more in 1874–7, to provide berths for
ships unable to moor alongside the curved walls (plan
B). (ref. 224) They were set obliquely because of the dock's
limited width. There were also floating iron jetties. By
the 1890s the dock had come to be used largely for lyingup, and the jetties had all been removed by 1907. (ref. 225)
Proposals for improving the Export Dock were rejected
in 1881 and 1899, other works taking precedence. (ref. 226)
The western two-thirds of the Export Dock north
quay (1,608ft) was improved as part of the PLA's first
programme of works. A 20ft-wide Hennebique reinforced-concrete 'false' quay was designed by Frederick
Palmer and built by A. Jackaman & Son in 1912 14 at
an estimated cost of £21,950. It is a single row of
cylinders, like those at the Import Dock north quay, with
cross-braces and struts to the wall. Associated with this
work was a programme of dredging and impounding to
deepen the dock to 28ft. (ref. 227) The 'false' quay was extended
eastwards to the Bellmouth Passage by John Mowlem &
Company in 1938–9 and later was extensively repaired
following wartime bomb damage. The coping on the
south side of the dock was replaced in granite-concrete
in post-war repairs. Surviving south quay bollards may
be from that period, although they are of the type used
from 1912 at the Import Dock. (ref. 228)
Plans for partial filling of the Export Dock in the 1960s
and 1970s were not executed, and the dock was listed
Grade I in 1983. (ref. 229) Much of the 1804–6 walling survives,
little altered below the coping, though the north quay is
hidden beneath the decks of Canary Wharf.
Blackwall Basin
The Blackwall Basin was the first impounded, or nontidal, dock entrance basin ever built. In effect it served
as an enormous entrance lock. A number of ships could
be locked into the basin around high tide, remain afloat
there when the tide receded, and then lock into the docks
when convenient, without affecting the water level in the
docks. Ralph Walker visited Liverpool in 1799 and noted
the inadequacy of tidal entrance basins, reporting that 'I
see nothing worthy of being copied from the Liverpool
Docks'. (ref. 230) The basin was excavated by Holmes & Bough
in 1800–1 to provide a depth of water of 23ft, to match
the docks. It was not walled; the banked sides were
simply puddled. (ref. 231) At six acres it was almost as large as
the Queen's Dock at Liverpool of 1795, but in the context
of the West India Docks it seems little more than a large
pond. Its banks have been altered, but it remains close
to its original irregular oval shape, which facilitated the
towing in of ships.
Consideration was given to wharfing or quaying part
or all of the north side of the basin in 1817, and again
later in the nineteenth century. (ref. 232) A jetty was built in
1828, another was added sometime between 1841 and
1863, and, in the 1870s, the south-east corner of the
basin was walled. Nothing else was done, despite the
increasing risk of large vessels grounding, until more of
the south bank was reclaimed and quayed c1890. The
north side was walled in 1901 to serve as a barge berth,
and the south-west bank was quayed in 1927 8. (ref. 233) The
Blackwall Basin has remained virtually unused and
unaltered since the 1960s.
Blackwall Entrance Lock
The entrance to the West India Docks from the river at
Blackwall was the most critical point of the original dock
system. The fortunes of the dock proprietors turned on
its suitability for shipping. The original intention was to
provide a gated entrance, but in late 1799 it was decided
that a lock should be constructed, to provide greater
control over water levels and to reduce silting. (ref. 234) Excavation of the lock pit began in 1800, before Jessop and
Walker had settled the dimensions of what was to be the
largest lock in England, at 45ft wide, 191ft 6in. long and
23ft 3in. deep at high water. (ref. 235)
The lock pit was ready for its timber foundations, contracted to John Bunn, in June 1801, but timber was then
scarce. Great difficulty was experienced in getting beech
transported from the Ashridge estate in Hertfordshire, and
oak for the 28ft-tall lock gates had to be obtained from the
Royal Dockyards and private shipbuilders. (ref. 236) The dock
company pushed hard for progress, but the delays were
such that Bunn's contract was transferred to Thomas
Clark, of Woolwich. Adam and the Robertsons were
responsible for the brickwork and Dundee gritstone
masonry, and Allan MacFarlane carried out the ironwork. (ref. 237) In late 1801 William Bough and Thomas Clark
built a coffer-dam, to allow Adam and the Robertsons to
build the outer wing walls. It consisted of two sections,
each about 120ft long, linked by the remains of a wharf. (ref. 238)
Pressure to complete the works increased in 1802, and
Jessop prematurely ordered dredging that may have led to
the breach of the coffer-dam on 22 July which killed six
men. This did not prevent the company from opening the
lock on 27 August. (ref. 239)
The 1801–2 Blackwall entrance lock was founded on a
timber platform and piles supporting the brickwork of a
broad inverted arch, squared for the sills of the gates (Plate
46c; fig. 96b). This form of lock construction, in which the
invert acts as a strut between the walls, had been established
in late-eighteenth-century canal building and the detailed
design was presumably by Jessop. The separately centred
'banana' side walls were strengthened by counterforts and
their upper parts were faced with massive ashlar blocks. (ref. 240)
The widely spaced wing walls, also of 'banana' section,
were not stabilized by any platform or apron. They were
probably faced with latticed timber fenders.
Within months of the opening, John Rennie reported
operating problems at the Blackwall entrance, as well as
cracks in the south outer wing wall, (ref. 241) part of which
collapsed in 1807. (ref. 242) To avoid disrupting business, it was
not properly rebuilt. The lock required many more
repairs, perhaps a reflection of the haste with which it
was built. The stability and soundness of the entrance
was indeed a constant worry, but nothing significant was
done, chiefly because, as there was no other down-river
access to the docks, closure for rebuilding was regarded
as too costly in terms of lost business. (ref. 243) The lock gates
were replaced in 1812, and again in 1864 by Westwood,
Baillie & Company, presumably in iron. (ref. 244)
The pierheads were improved in 1824–5 to plans by
(Sir) John and George Rennie. On the south side, a
timber jetty was added, and a section of river wall, 137ft
long, was rebuilt in brick. The north wing wall was
extended and given new river stairs. (ref. 245) The Edinburgh
Steam Packet Company used the south pierhead as a
platform for steamboat passenger services until 1835,
when the facility was superseded by Brunswick Wharf. (ref. 246)
The fabric of the Blackwall entrance was one problem;
as ships grew larger its size became another. On 11 August
1851 the north outer wing wall collapsed, probably because
of seepage from Poplar Dock. The dock company was
forced to send some shipping round to Limehouse. (ref. 247) The
directors were so alarmed by the vulnerability of their principal entrance that they sanctioned an immediate call to
the eminent dock engineer James Meadows Rendel. Foreseeing both increasing competition and yet larger steamers,
Rendel tried to persuade the company to build a wholly new
entrance, 60ft wide. However, company officers, including
Henry Martin, favoured the Junction Dock as a means of
reducing dependence on the Blackwall entrance (see page
280). (ref. 248) Dockmasters believed that ships then docking at
the East India Docks were 'larger than ever we shall see
again'. (ref. 249) Rendel's proposal was rejected and, in 1852–4,
both wing walls were repaired. On the south side, Rendel
introduced campshedding reinforced with iron wales and
tied back through the old wall to massive counterforts of
concrete on ragstone footings. The counterforts were about
12ft to 15ft square. An open timber platform was used in
lieu of walling on the north side. (ref. 250)
The primacy of the Blackwall entrance was ceded to
the rebuilt South Dock east entrance in 1870. The
Blackwall entrance lock fell into such bad repair that it
could only be operated on a level tide. (ref. 251) The London
and India Docks Joint Committee turned its attention to
the problem in 1892. A larger lock was needed for the
sake of the whole West India Dock system, for the South
Dock east entrance was already out of date. The Blackwall
entrance lock was rebuilt in 1892–4 as part of a larger
scheme which included impounding to raise the level of
water in the docks. (ref. 252)
Robert Carr consulted the dockmasters and worked up
plans for an entrance lock 430ft by 60ft and 30ft deep at
high water, with intermediate gates to give an outer lock
280ft long and an inner one 150ft long. This arrangement,
later reversed, allowed the economical locking of small
vessels. He estimated the costs at £88,434 for the lock
and £155,814 for the whole project. On the basis that
Lucas & Aird were 'the contractors best acquainted with
Dock Work in the Port of London', they were given the
main contract, for £80,000. No other tenders were
invited, despite the objections of Carr and others within
the dock company. (ref. 253) Work started in September 1892
and coffer-dams of clay puddle between lines of cast-iron
sheet piling went up quickly. (ref. 254) Following representations
from Donald Currie & Company, whose ships measured
450ft, the Joint Committee decided in 1893 to lengthen
the lock to 480ft, divided as an inner lock 280ft long and
an outer one 200ft long, at an extra cost of £8,700,
pushing the pierhead further into the river. (ref. 255) The new
lock walls were built outside the old walls, which were
subsequently removed (Plate 46c). (ref. 256)
Robert Carr suffered a stroke in October 1892. He was
retained as a consultant to see the Blackwall entrance
works to completion, but Sir Alexander Meadows Rendel
was brought in to design three pairs of lock gates,
constructed and erected by the Thames Iron Works &
Shipbuilding Company. (ref. 257) The lock's hydraulic machinery was supplied by Sir William Armstrong & Company.
It comprised six direct-acting gate rams, of a type which
was novel at the time, six sluice valves, four 5-ton
capstans and 12 fairleads. (ref. 258) Many of these fittings survive,
with cast-iron bollards, presumably contemporary and
probably supplied by the Butterley Iron Company. (ref. 259) (fn. c)
The rebuilt Blackwall entrance lock opened for business
on 16 August 1894. (ref. 261) The final cost of £208,799 included
£141,753 for the lock and related works by Lucas & Aird,
£12,274 for the gates by Thames Iron Works, and £7,519
for Armstrong & Company's hydraulic machinery. (ref. 262)
The 1893–4 lock, which survives, is built of mass
concrete with blue brick facings (Plate 46c; fig. 96g). The
straight-sided walls are up to 36ft thick and the invert,
7ft thick at its centre, has 3ft of gault brick over the
concrete. There are Cornish granite and Brigg stone
dressings, and brick-lined culverts for scouring the outer
gate floors and apron at low tides. Knuckles at the west
end of the lock were intended to permit later extension.
The semi-buoyant and double-skinned cellular gates have
steel framing and wrought-iron casing and are divided
horizontally into three compartments, the middle air
chamber and upper section open to water on one side to
prevent excess buoyancy. Each gate is 37ft 6in. tall and
weighs approximately 80 tons. (ref. 263) To improve docking, a
timber jetty, 140ft long, was built from the north pierhead
in 1899–1900 by John Price for £2,560. It was rebuilt by
Holloway Brothers in 1923–4. (ref. 264)
The Blackwall entrance became much less important
after 1929, following the completion of a new South Dock
east entrance and passages linking the Import, Export and
South Docks. It was closed from 1940 to 1950, reopening
only for barge traffic. In 1960–1 John Mowlem & Company
repaired 270ft of the lock's south wall in reinforcedconcrete, re-using the granite coping. (ref. 265) The lock was last
used in 1968. The LDDC removed the middle gates and
permanently dammed the lock under a bridge in 1987, as
part of improvements to Preston's Road.
Limehouse Basin
The two-acre basin that was formerly at the west end of
the West India Docks accommodated lighters and empty
ships passing between the docks and up-river quays. It
was not necessary for the opening of the docks and so
was built slightly later than the Import Dock and Blackwall Basin. John Dyson and Holmes & Bough excavated
it in 1801. Unlike the Blackwall Basin, it was given
brick walls, of 'banana' section, built by Adam and the
Robertsons in 1802. It was coped with Portland stone, as
Dundee stone was in short supply. (ref. 266)
The Limehouse Basin was not completed until July
1803. largely because on 13 October 1802 a high tide
passed over and behind the uncoped south wall and,
though 4ft 6in. thick, part of it collapsed. Jessop blamed
Walker, claiming that the walls had been laid 22in. lower
than he had specified. John Rennie was called in to report
on the incident, and in doing so he made extensive
criticisms of the work. He stated that the wall should
have been thicker and more markedly curved, and that
stone bonding-courses should have been used. The dock
company remained cautiously loyal to Jessop, but asked
him to consult Rennie in future. (ref. 267)
The Limehouse Basin was 21ft deep at high water,
and the walls rose 6ft higher. Rennie's advice may have
been heeded, as the rebuilt south wall was about 5ft 8in.
thick, with ashlar blocks, about 6in. by 18in. at the
face, at 6ft intervals about 4ft below the coping. Jessop
evidently declined to use continuous ashlar bondingcourses as employed by Rennie at the London Docks.
The wall had counterforts, 3ft wide, at 9ft 6in. to 13ft
6in. centres, with reinforcing iron hoops. (ref. 268)
Enlargement of the Limehouse Basin was considered
in the prosperous 1810s, and again in 1864, when congestion by lighters was a serious problem. (ref. 269) However,
nothing was done, and after the Limehouse entrance lock
closed in 1894 the basin was little used. It survived as a
lay-by for barges and repair of boats, and as a cut between
the Import and Export Docks. Sheds were built on its
south side in 1901–2, bringing some use as wharfage. (ref. 270)
The Limehouse Basin was filled in 1927–8, to save on
maintenance and to increase storage ground, using
material from the excavations for the Millwall Passage. (ref. 271)
Limehouse Entrance Lock
The Limehouse entrance lock was built principally for use
by lighters and was therefore smaller than its Blackwall
counterpart. It was only after the docks opened in August
1802 that attention turned to the secondary problem of
access from Limehouse. Holmes & Bough excavated the
pit, Thomas Clark built the timber foundations, and
Adam and the Robertsons built the invert and walls. The
outer wing walls were built without using a coffer-dam,
on piled foundations at low-water level. (ref. 272) The lock was
completed by mid-1803 and was 36ft wide, 155ft long
and 22ft deep at high water, and followed the Blackwall
lock in form and materials. (ref. 273)
The hurriedly built and inadequately founded outer
wing walls were entirely rebuilt with a stabilizing stone
apron in 1809–11, on John Rennie's advice. The estimated
cost was £9,800. (ref. 274) William Bough contracted for the
work, but a large part of his coffer-dam gave way because
he had not driven his piles deeply enough. (ref. 275) The contract
was transferred to William John Jolliffe and Edward
Banks, who were described by Rennie as having 'much
experience in the building of Bridges'. (ref. 276) (fn. d) The rebuilding,
including arbitration against Bough, finally cost
£29,361. (ref. 278) Iron lock gates, an early example, were fitted
at that time, and were not replaced until 1870. (ref. 279)
The Limehouse entrance lock closed in 1894, immediately following the opening of the rebuilt Blackwall
entrance lock. Continued operation would have reduced
the effectiveness of the new impounding system. (ref. 280) It
remained closed despite Frederick Palmer's proposal in
1911 that it should be reopened. (ref. 281) The filling in of the
Limehouse Basin in 1927–8 made it quite useless. It was
dammed and filled in 1930 by J. J. Prior Ltd, who leased
the site to be part of Bridge Wharf (see page 394).
Inner Locks
The inner lock from the Blackwall Basin to the Import
Dock (Blackwall Import lock) was built in 1801–2 by
Adam and the Robertsons, on timber foundations by Job
Leader. It was originally 37ft 3in. wide, 162ft long and
24ft 3in. deep at high water. It differed from the river
entrances in having an elliptically arched invert. (ref. 282) Its
gates were replaced by Henry Jeffrey in 1815, and gritstone copings were replaced with Aberdeen granite in
1823. (ref. 283)
The Limehouse Import lock was built in 1801–3 by
Adam and the Robertsons, on timber foundations by
Thomas Clark. It measured 150ft 3in. long, 36ft wide,
and 22ft deep at high water. (ref. 284) New gates were provided
in 1819. (ref. 285)
The Export Dock inner locks were built with the
Export Dock in 1804–6, to Jessop's specifications.
Thomas Clark built the timber foundations and cofferdams. Aslat, Collins, Gill & Steward carried out the
brickwork, and Thomas and William Crawford the
masonry, using Cornish granite. The Blackwall Export
lock was 38ft wide, 160ft long and 21ft 9in. deep at high
water; the Limehouse Export lock was 36ft wide, 151ft
long and only 18ft deep at high water. (ref. 286)
Widening of the Blackwall Import lock to allow larger
ships into the Import Dock soon came under consideration. Part of the lock coping was trimmed off in
1837 to facilitate the docking of larger ships. (ref. 287) After a
ship had stuck in the lock in 1884, eight inches of stone
and brick were chipped away below water level on each
side, a practice said to have come from Liverpool. (ref. 288) The
works carried out in 1892–4 for improving access to the
Import and Export Docks included the enlargement of
the Blackwall Import and Export locks as open passages.
The introduction of impounding left no reason for locking
between the Blackwall Basin and the docks. Solid inverts
were unnecessary, and so it was proposed that the south
side of the Import passage and the north side of the
Export passage be reconstructed in timber wharfing,
leaving the opposite sides unaltered. (ref. 289) These plans were
recast by H. F. Donaldson in 1893 to use concrete,
following difficulties, perhaps with pile-driving,
encountered by Lucas & Aird, contractors for the work.
The cuts, completed in 1894, were 60ft wide and 27ft
deep, with inverts where railway bridges crossed. Castiron mooring bollards were supplied by the Butterley
Iron Company. The cost was £33,805, more than double
the original estimate. (ref. 290) The mass-concrete walls are 4ft
6in. thick at the top and 15ft at the bottom. They have
battered and curved sides, and Cornish granite coping. (ref. 291)
The Blackwall Export passage was rendered superfluous when the Bellmouth Passage was made in 1927–9,
and so was filled in. (ref. 292) The Blackwall Import passage
survives. The Limehouse Export lock was filled in 1927,
and the Import lock survived as a dead-end passage until
1964. (ref. 293)
West India Dock Graving Dock
The prohibition on shipbuilding and repair within the
West India Docks was no longer justified once the Victoria
Dock, in the 1850s, and then the Millwall Docks, in
the 1860s, were allowed integral ship-repair facilities.
Shipowners found it convenient to use dry docks within
wet docks, and so those without such a facility were
likely to suffer in an increasingly competitive port. Donald
Johnson & Company, shipbuilders at the Regent Dry
Dock (see page 418), approached the East and West India
Dock Company in 1872 with an offer to build and lease
dry docks on the south side of the Blackwall Basin. The
dock company thought the site unsuitable and considered
making the dry docks itself. (ref. 294) Indeed, in 1874 it obtained
an Act empowering it to build and maintain its own dry
docks, (ref. 295) although it subsequently invited others to make
and lease them. Johnson & Company first submitted
plans for a dry dock east of the Junction Dock off the
South Dock Basin, but the dock company decided to
retain this site for wood storage and so Johnsons proposed
a single large dry dock off the Blackwall Basin. This was
approved in August 1875, and Johnsons were granted a
lease of an irregular site, including the east end of the
Saltpetre Warehouse, and a frontage of 415ft on to
Preston's Road south of Longley Place. The lease was
for 99 years from one year after the opening of the dry
dock, and the annual rent was £1,292. (ref. 296)
Johnson & Company began work on the dry dock in
early 1876 with a capital of £70,000. Donald S. Baynes
was the engineer and Merritt & Ashby the building
contractors. Augustus Manning, for the dock company,
objected to the proposed depth of only 19ft 9in. and,
following advice from Charles Hampden Wigram, a dock
company director and shipbuilder, it was revised to 23ft.
The West India Dock Graving Dock opened on 6 March
1878. (ref. 297) It was 452ft long and 63ft wide at the top of its
entrance. Its internal width was 80ft at the bottom and
94ft at the top, so that it was broad enough to accommodate two large steamers at once. It was one of the
largest dry docks in the country, and only the Thames
Ironworks had a larger dry dock in London (figs 96f,
97). (ref. 298) The dock was largely mass concrete, with 11ftthick foundations on a timber floor, sides up to 13ft
thick, faced in brick with York stone altars, teak coping
and granite quoining. It had a chambered wrought-iron
'ship' caisson, flat on the dock side with a vessel-like
section to the basin. A culvert, 600ft long and 5ft high,
ran from the dockhead to the South Dock pierhead.
Further drainage was by means of a large centrifugal
pump, made by Gwynne of Hammersmith, placed in a
small pump-house east of the dock. There were hand
capstans and mooring posts on the quays. Otherwise the
site had only simple timber sheds and a small steam
crane. (ref. 299)

Figure 97:
West India Dock Graving Dock (1876–8), plan in 1935Key: A Platers' shop B Offices: C Stores and Plumbers' Shop: D Offices and Caretaker's Flat: E Carpenters' Shop:F Fitting Shop: G Blacksmiths' Shop: H Furnaces
Johnson's earlier partners were succeeded by John
Denison Pender and Frank Gooch in 1877–8. The
company was soon in financial trouble. The dock company
refused to buy the dry dock, and in 1879 the lease was
mortgaged to Pender, James Rankin, and Sir Daniel
Gooch, for £74,200, then assigned to Pender alone in
1880. Pender reconstituted his ownership under the West
India Graving Dock Company, registered in 1883. (ref. 300) He
was one of the founding directors of the Dry Docks
Corporation of London, formed in 1886 to amalgamate
28 London graving docks and thereby create a monopoly.
The lease of the West India Dock Graving Dock was
transferred to the new company for £40,000. Business
was then slack, however, and the Dry Docks Corporation
was voluntarily wound up in 1888. (ref. 301)
In 1890 the lease of the West India Dock Graving
Dock was assigned to A. Chivas Adam, a shipowner, who
formed and became first chairman of the London Graving
Dock Company, to which the property was reassigned. (ref. 302)
The company also leased additional property along Preston's Road, including four of the Longley Place cottages,
from the dock company. The area around the dry dock
was developed with new buildings and plant in 1891.
The southern pair of cottages was demolished and a brick
machine- and fitting-shop was built backing on to the
road; to its south was an earlier long low ironsmiths'
shop (fig. 97). The central pair of cottages became offices
and a caretaker's flat, with a new two-storey joiners' shop
immediately to its west. In 1893 Gwynne pumping
machinery, a boiler-house, and a 75ft-high chimney were
erected on the east side of the dry dock, with a new
culvert to discharge into the Blackwall Basin. (ref. 303)
The London Graving Dock Company extended its
West India Dock premises westwards in 1917, at the
request of the Admiralty, with a berth at Blackwall Basin
and the remains of the bomb-damaged former Saltpetre
Warehouse, repaired and refitted as a platers' shop in
1918–19 (fig. 97). (ref. 304) A 15-ton electric travelling crane
supplied by Sir William Arrol & Company was erected
alongside the dry dock in 1933. (ref. 305) The site suffered heavy
bomb damage in 1940–1. By 1943 new offices and a
fitting shop had been built, and the remaining Longley
Place cottages cleared to accommodate an access road
and a smiths' shop. (ref. 306) In 1945 the London Graving Dock
Company, needing more space, took a lease of No. 1
Teak Shed, west of the dry dock. It was rebuilt in steel
and occupied by two subsidiary companies. More steel
shedding was erected on the Saltpetre Warehouse site,
for a platers' shop, and further west for a sawmill and
timber store. (ref. 307) The damaged dry dock remained in use,
though it was itself in need of repair. It was reconstructed
in 1948–9, when the works were supervised by F. W.
Davis and executed by George Wimpey & Company
for £24,000. The splay end wall was moved closer to
the road to increase working space. (ref. 308) The premises
were extended further across the former teak ground in
1951. (ref. 309)
When the ship-repair industry was nationalized in
1977, the London Graving Dock Company was acquired
by British Shipbuilders and made part of River Thames
Shiprepairers. However, continued use of the West
India Dock Graving Dock depended on continued use
of the wet docks. With their business declining
dramatically, operations were wound up and the lease
of the dry dock was surrendered in 1979. (ref. 310) The caisson
was removed and the workshops were demolished in
1985–6. (ref. 311) A permanent bridge was erected across the
graving dock in 1988, the premises having been
redeveloped for housing.
South Dock (formerly the City Canal)
The South Dock is the southernmost of the three principal docks in the system. It originated as the ship canal
built across the Isle of Dogs by the Corporation of
London in 1800 5 (fig. 91). The construction of the City
Canal was managed by George Dance for the City's
Committee for Improving the Port of London. The
engineer for the works was William Jessop, with John
Foulds as his assistant, succeeded by Daniel Vaux from
1803. (ref. 312)
Preliminary excavation of the canal started in 1800, by
John Clark and Thomas Thatcher, from Wiltshire, and
some direct labour. The main excavation and embankment work was contracted to John Dyson, of Bawtry,
Yorkshire. He was not able to begin until 1801, because
of delays with the installation, supervised by John Rennie,
of a Boulton & Watt steam pumping-engine on the site
that later became the Canal Dockyard. (ref. 313) The City did
not match the zeal and assiduity of the West India
Dock Company. Because of the need for further funding
through Parliament, and for additional pumping power,
work on the canal's entrance locks did not even commence
until 1803. The main excavation was completed in 1804,
and the locks were approaching completion in July 1805
when the coffer-dam and preventer dam at the east end
failed, causing a great wave to rush through the canal.
Extensive repairs were needed and the opening had to
be postponed until 9 December 1805. (ref. 314) The canal was
3,711ft long between the lock gates, 176ft wide at the
surface of the water and 23ft deep at its centre, dug only
17ft down, with the spoil used to build up the banks. It
cost £133,850 to build, and £34,963 was spent acquiring
the land. (ref. 315) (fn. e) James Mountague, one of Dance's clerks,
took up the post of Surveyor and Superintendent of the
Canal, with a house over the Canal Office in Coldharbour. (ref. 317) He became a prominent and influential local
inhabitant, remaining Superintendent of the canal until
1828. (ref. 318)
The City Canal was not a success, for it was not
adopted as a worthwhile short cut. Its potential had
probably been overestimated, and London's growing
number of wet docks and the arrival of steamers in the
river further reduced its usefulness. From 1811 it became
primarily a 'receptacle for dismantled ships'. (ref. 319) In 1812
13 the north-east pierhead was made a wharf with a
crane, for the deposit of anchors, mooring chains and
stones, as part of the City's general duties in the Port.
Harbour-master's offices resembling small gate lodges
were erected on other pierheads. (ref. 320)
From 1806 the City attempted to increase revenue by
selling and letting surplus property near each end of the
canal. In 1816 it began to let plots on the north bank of
the canal itself, despite the West India Dock Company's
objections respecting security and fire risks (only 100ft
separated the canal from the Export Dock). (ref. 321) The plots,
generally about 100ft by 50ft, were let as boatbuilding,
cooperage, timber, coal and stone yards, with sheds,
warehouses and workshops built upon them. (ref. 322) The canal
continued to be used for some transit and for the layingup of ships, particularly whalers, but the provision of
water frontage for these small wharves seems to have
been its principal function in the 1820s. (ref. 323)
The City's Port Committee was keen to dispose of the
canal altogether. In 1809 the Treasury was persuaded
that a sale would limit losses, and two groups of merchants
offered to buy it for conversion into a wet dock. However,
the Society of Ship Owners of Great Britain wanted the
canal, however little used, to remain for transit and
blocked the sale. (ref. 324) The West India Dock Company
became interested in the canal in 1815, with an eye to a
convenient bargain as well as to its need for extra
accommodation for its export business. John Rennie
prepared plans for linking the canal and the Export Dock,
but negotiations with the Treasury foundered on the
company's proposition that its purchase of the canal be
tied to a renewal of its monopoly charter. (ref. 325)
The situation was transformed in 1823, when the
company's monopoly expired. The canal, as the basis for
a new dock, represented a threat to the company and an
opportunity for competitors. The company was by then
in urgent need of more space for export business, and in
1824 it asked the Treasury for permission to annex the
canal. This was refused, as there were other interests in
the field, in the shape of schemes for collier docks. (ref. 326)
The rapid growth in sea-coal traffic during the early
nineteenth century brought increasing congestion to the
river's collier pool. It was estimated that the number of
colliers in the river had increased from 3,452 to 7,117 in
the 30 years to 1824. (ref. 327) The precedent for the dedication
of docks to particular trades made collier docks a possibility. Promoters of a collier dock scheme had offered to
buy the City Canal in 1812 and had introduced a Bill,
which included a 'compulsory clause', into Parliament,
but the City had combined with the coal-buyers to defeat
it. (ref. 328)
Collier dock schemes, most of them calling for the
appropriation and adaptation of the City Canal, were
given more serious consideration in 1824–5. (ref. 329) The five
competing proposals were reduced to one, prepared by a
consortium of owners and occupiers of land in the Isle
of Dogs who were anxious not to be deprived of profits
to be made from their property. This group was led by
George Byng, William Mellish and Thomas Tooke, with
George Rennie employed to design and ambitious scheme
that proposed the largest dock system in London across
the northern half of the Isle of Dogs, south of the City
Canal. There was to be space not only for the coal trade,
but also for some timber and other foreign trade, gleaned
from the expiring monopolies of the existing dock companies. Rennie proposed two parallel rectangular docks
with surrounding warehouses, east and west basins, and
two river entrances on each side. The canal was to be
retained for transit, with two communicating cuts. (ref. 330)
The scheme was vigorously opposed in Parliament,
resistance coming from the coal trade, particularly the
Newcastle Coal Vend, and shipowners, who objected to a
'compulsory clause'. The City opposed the Bill, ostensibly
because of the effect collier docks would have on the
price of coal, but also because it wanted to auction the
canal. (ref. 331) The West India Dock Company also opposed
the scheme, fearing the competition. Nevertheless, an
Act for the Collier Dock Company was passed in June
1825, but without the 'compulsory clause'. (ref. 332) The start
of work was conditional on the raising of the full capital
of £600,000, 80 per cent of which had been subscribed
prior to the suppression of the 'compulsory clause'.
However, without the power to compel use of the dock,
and in a difficult economic climate, the balance could not
be raised, and the Collier Dock Company collapsed in
1827. (ref. 333)
The City then considered letting the canal to Charles
Moore, as docks and yards for the softwood trade, but
by 1829 the Treasury had decided that sale of the canal
was preferable. Moore and William Mellish both offered
£110,000, and the City even considered paying the
Treasury £120,000 for it. (ref. 334) The dock company then
sprang into defensive action, nervous of the possible fire
risks, as well as the commercial consequences of such a
sale. (Sir) John Rennie advised the company that the
canal was 'worth more to You than to any person else'
and revived his father's suggestion that a link could be
made to the Export Dock, recommending that the canal
become a depot for Baltic timber and laid-up shipping. (ref. 335)
In a state of high anxiety, the dock company sent the
Treasury a blind tender for £120,000, and, as no other
tenders were submitted, in March 1829 it acquired the
canal. (ref. 336) The Act for the sale included provision for the
company to borrow £500,000 for improvements. (ref. 337)
The canal was renamed the South Dock immediately
the dock company took possession in August 1829.
Transit passage was stopped, and the tenants of the banks
and their sheds were removed. The intention to make
the canal an extension of the Export Dock via a connecting
cut remained. However, Charles Moore approached the
company with a scheme for adapting the south bank for
the storage of bonded softwood. He was rebuffed, but
his idea was not. (ref. 338) By 1831 the South Dock was full of
floated timber and, under Thomas Shadrake, up to 20
jetties had been built along the length of the north bank,
some with fixed cranes. (ref. 339)
The prospect of growth in the softwood trade led to
the building of a pond for floated timber on the south
side of the South Dock. Shadrake put forward a proposal
in 1831 to which (Sir) John Rennie added his own
suggestions. A 19-acre pond was projected, the length
limited by Joad & Curling's ropewalk, the width by the
dock company's boundary. (ref. 340) Rennie looked at the timber
ponds at the Commercial Docks, then, with his brother
George, submitted detailed plans, with an estimated cost
of £6,825. They designed a 16-acre pond, 2,030ft by
410ft, 8–10ft deep at high water, with sides banked at 30
degrees and a brick-lined and gated entrance, 31ft wide,
from the centre of the South Dock. The building contract
went to Hugh and David McIntosh, against the Rennies'
recommendation. (ref. 341) (fn. f) The work, supervised by Shadrake,
was carried out in 1832–3. (ref. 343) After wind damage, and
advice from (Sir) John Rennie, in 1835 the east bank of
the pond was reinforced with Kentish ragstone paving. (ref. 344)
The banked south side of the South Dock remained
unusable for wharfage. When guano sheds were built
along the western half of the south bank in 1850, they
were made accessible to shipping by the construction of
500ft of quay wall with Kentish ragstone re-used from
the former settling reservoirs, at this date being rebuilt
as Poplar Dock. Part of the north bank at the east end
was campshedded in 1854–5, following the abandonment
of more extensive improvements proposed by James
Meadows Rendel in association with the building of the
Junction Dock. (ref. 345)
The South Dock was entirely rebuilt in 1866–70, when
the inadequacies of the whole dock system had become
so manifest that investment in major improvements could
no longer be deferred. In June 1864 it was proposed that
the South Dock should be deepened, with basins and
larger entrances for export business. It was agreed that
this work should be undertaken 'sooner or later', with
other improvements, including enlargement of the East
India Docks and the Limehouse Basin. The Dock Superintendent, William Hickson, and other officers developed
the scheme to include the widening of the South Dock
at both ends. From December 1864 the company retained
the services of Sir John Hawkshaw, for advice on the
Millwall Extension Railway Bill and 'other matters of
improvement'. His attention was largely directed to the
South Dock. He prepared two plans for extending it to
the south-east, without quay walling, and with or without
a half-tidal basin. The company obtained an Act to
improve its ability to raise money for large works, and
formed a Special Committee on Dock Improvements.
When Hawkshaw's and the company officers' plans for
the South Dock, and another for improving the East
India Docks, were considered in December 1865 no
single scheme was approved, but a commitment was
made to transfer export business from the East India
Docks to an enlarged deep-water South Dock with a
basin. This would accommodate large steamships, with
space for the numerous lighters filling the docks, and
quay room for much-needed warehouses. (ref. 346)
Hawkshaw's schemes required the acquisition of land,
with consequent delay and expense, and in early 1866
they were heavily modified, if not wholly redesigned, by
the company's officers. They had submitted a plan for
the adaptation of the Timber Pond, which Hawkshaw
adopted and worked up to a form close to what was
eventually built. The former canal and the Timber Pond
were to be replaced by a large walled dock with an eastern
half-tidal basin, laid out so that the projected Millwall
Extension Railway would run between the basin and the
dock. The north side of the dock was to be equipped
with 16 130ft-long timber jetties, comparable to those at
the Royal Victoria Dock, and given over to export business. On the south quay there would be five warehouses
for East India imports. Hawkshaw estimated the cost of
the plan at £450,000, with an additional £100,000 for
warehouses. The scheme was approved on 25 May 1866,
a fortnight after the financial crash in the City, which
appears not to have hampered the project at all. (ref. 347)
The contract for the South Dock rebuilding was given
to George Wythes, of Bromley, in August 1866 for
£338,000. (fn. g) Work commenced in October 1866, with
Leveson Francis Vernon-Harcourt as Hawkshaw's Resident Engineer. By the end of 1867 the dock company
was complaining about the rate of progress. (ref. 349) Wythes
responded robustly, accusing the directors of being
'excessively illiberal in their dealings with me, they do
not try to assist me in anything connected with the
progress of the Works, but suffer nevertheless like the
man at sea, who having insured his life, was regardless
of the fate of the Ship'. (ref. 350) Pumping the excavations was
particularly difficult, with a large influx of water from
the recently filled Millwall Docks. Further delay resulted
from an accident on 7 September 1868, when 600ft of
the new south quay wall slipped forward. This was
attributed to water pressure from the Millwall Docks,
but Wythes had to bear the expense. (ref. 351) Despite a second
slip of about 100ft of south quay wall in March 1869,
the South Dock was finished by August 1869, though
not open to shipping until 5 March 1870, once the new
east entrance lock was completed. The cost of the dock
and lock works, including hydraulic machinery, was
£512,353. The whole South Dock project, including
warehouses, bridges and railways, cost £604,168. (ref. 352)
The rebuilt South Dock covered 26¾ acres, 2,650ft by
450ft, and was 29ft deep at high water, with a basin of
5½ acres, 600ft by 370ft. Hawkshaw's walls have slightly
battered straight sides, better suited to contemporary
shipping than the early nineteenth-century 'banana'
section walls (fig. 96d). They are approximately 35ft high
and 11ft 6in. thick at the top, and have an unusual
constructional form. There are square brick pockets filled
with mass concrete; the face is 3ft 6in. thick and the back
1ft 2in. thick, linked by counterforts or cross-walls, 2ft
4in. thick, at 10ft centres. The whole wall rests on massconcrete foundations, 3ft 6in. thick. (ref. 353) The rebuilding
used 61 million stock bricks. (ref. 354) Bramley Fall stone copings
were progressively replaced with granite from 1878. (ref. 355)
The concrete pocket walls, although cheap to build, were
not highly regarded. An alternative method of integrating
concrete and brick was used at the Surrey Commercial
South Dock (1851–5) and at the Millwall Docks (1865–
8) and was considered more successful (see page 354).
Dock engineers and builders were, in any case, learning
to eliminate brick from dock walls. (ref. 356)
Berths at the export jetties on the north quay of the
South Dock, and at the South Dock Basin, were let to
large shipping companies. To meet demand, more berths
and longer jetties were needed, resulting in 'a neck-ornothing race between the urgent demands of the public
for more accommodation and the efforts of the Company
to supply it'. (ref. 357) The success of the South Dock was shortlived. Within a decade it was unable to accommodate the
largest steamers on the river because of the length of its
lock and the positioning of the jetties. Its business moved
to the Royal Albert Dock from 1880, (ref. 358) and the jetties
were removed between 1884 and 1915. (ref. 359)
The decline of the South Dock was slowed, but not
stopped, by the enlargement of the east entrance lock in
1900–2. It remained a resort of the last of the large sailing
vessels arriving in London, but by 1910 it was in 'practical
disuse'. The PLA and Frederick Palmer then prepared
plans for its revitalization, with a new entrance lock, a
remodelled basin, a dry dock, and a new south quay. The
work was deferred for lack of funds, redesigned by
C. R. S. Kirkpatrick in 1914–15, but then, after the
estimated costs had more than doubled, suspended
altogether in 1920. (ref. 360)
The West India and Millwall Docks Improvements
Scheme of 1924, prepared by D. J. Owen and Kirkpatrick,
then revised by Palmer, set out to improve the dock
system by the more modest means of an enlarged entrance
lock and new passages between the docks. (ref. 361) The project
went ahead in 1927–9. In connection with the rebuilding
of the South Dock east entrance lock, the South Dock
Basin was effaced. The walls that separated it from the
South Dock were removed and new sections of massconcrete quay wall were built. Most of the quay copings
and bollards around the dock were replaced in 1929–30,
by A. Jackaman & Son. (ref. 362) Bomb-damaged sections of the
quays were repaired in 1942–3 and 1946. The surviving
quay bollards at the South Dock are the horn-shaped
'Bean' type (see page 354). Two variants are probably
datable to 1929–30 and 1946, the more bulbous being
the earlier. Dredging and impounding increased the depth
of the South Dock to 30ft 6in. in 1953 and to 31ft 6in.
in 1956. (ref. 363)
South Dock West Entrance (Impounding) Lock
The City Canal's entrance locks, presumably engineered
by William Jessop, were very similar to those he designed
for the West India Docks. The South Dock west entrance
lock is the only survivor of the whole group. It is
substantially unaltered, largely because it was never
heavily used; it has not been used for shipping since
1891. Since 1929 it has provided an inlet for water to an
impounding station that maintains the water level in the
West India and Millwall Docks; it is therefore known as
the Impounding Lock.
Until 1799 the plans for the canal provided for gated
entrances, but locks were eventually chosen, possibly
following advice from Trinity House that the entrances
should be 45ft wide. (ref. 364) The west entrance lock was built
by John Dyson in 1803–5. Early plans directed it upriver, but it was built in line with the canal. Earth
excavated from the canal site was used by David Gardener, of Islington, to make two million bricks for the
locks, and one million more were supplied by Henry
Stevens, James Butt and John Capel Hanbury, of Mile
End. Portland stone dressings for both locks were supplied and fitted by William Brown, of Smithfield. William
Stewart, of Poplar, built the external and internal wing
walls at both locks, his work continuing into 1806. The
coffer-dams were made by James Spedding, of Poplar. (ref. 365)
The lock was originally 192ft long between the gates
and 23ft 5in. deep at high water; it was, and remains,
44ft 10in. wide, large enough for the biggest ships on
the river in 1805. (ref. 366) In section the lock has a segmentally
arched invert and separately centred 'banana' side walls,
6ft thick, bonded to counterforts with iron hoops
(compare fig. 96b). The invert is supported on a timber
platform and piles. The original gates, their paths and
sills were all of oak, with the heel-posts turned in castiron sockets. (ref. 367) The upper 12ft or so of the lock chamber
walls are ashlar faced, with Bramley Fall mixed with
other stones, re-coped in granite. Next to the hollow
quoins of the outer gate recesses there are tide markers
in Roman numerals, outside which are chain-tunnels,
with vertical grooves beyond for the preventer dam (the
temporary wooden wall used to back up the coffer-dam
during construction and repair). The outer wing walls
are not tied to the lock walls; there is stone quoining at
the junctions. The wing walls are of 'banana' section
with counterforts. Each was built in two lengths, with
shallower foundations to the outer sections, built outside
the coffer-dam on timber piles with heads at low-water
level. The construction is comparable to that of contemporary wing walls at the Limehouse entrance to the
docks, and at the London Docks. (ref. 368) Within the wing
walls there are horizontal timbers, 15in. square; there is
also exposed timber lacing to which lattice fendering was
originally attached. Adjacent to the quoined return end
of the south wing wall there are stone river stairs,
probably built in 1809 with the wharf walling to the
Canal Iron Works (Cascades) site.
In 1856, when the outer gates of the lock had been
removed for repair, the inner gates gave way at low
tide and the South Dock suddenly emptied, scattering
shipping. New inner gates were supplied by Hack & Son.
The outer gates were replaced in 1863, by Westwood,
Baillie & Company, presumably in iron. (ref. 369) The dock
company considered rebuilding the lock in 1877-82, but
did not do so, perhaps because this was the least important
entrance at the West India Docks. (ref. 370) Its closure was
determined in 1887, but it remained open until 1891. (ref. 371)
The PLA's improvement scheme of 1911 included the
erection of an impounding station astride the South Dock
west entrance lock. The project was deferred for want of
finance, but was revived in 1925. The lock was permanently closed in 1926–8 when Charles Brand & Son
formed a mass-concrete dam, 15ft thick, between the
gates, containing three pump-discharge pipes and two
sluicing-culverts. The outer gates were removed. (ref. 372) The
lock has been a vital water inlet since then. In 1989–90
it was repaired and stabilized by the LDDC, with Trevor
Crocker & Partners as engineers. The work included the
formation of a permanent concrete floor several feet above
the base of the invert, and a dam between the wing walls.
South Dock East Entrance Lock
The lock at the east end of the South Dock is the only
remaining working lock in the India and Millwall Docks.
The present lock is the third rebuilding of that constructed in 1803–5 by John Fentiman, which was 192ft
long, 45ft 3in. wide and 23ft deep. (ref. 373) The first enlargement, to 300ft by 55ft and 27ft deep, came in 1869–70,
after the rejection of Sir John Hawkshaw's proposal for
a wholly new 60ft-wide entrance through the Canal
Dockyard site. The enlargement was no cheaper than a
new lock, but it was easier in terms of land and engineering. George Wythes rebuilt the lock, to Hawkshaw's
plans, for £101,960. (ref. 374) The old north wall was retained
behind a new brick facing, 9ft thick (fig. 96e). The south
wall was rebuilt, using brick and concrete in the same
manner as in the South Dock quay walls. The brick
invert was 3ft thick and rested on a concrete foundation,
and the gate floors and outer aprons were made of
Bramley Fall ashlar. There were hydraulically operated
cellular wrought-iron gates, 35ft high, manufactured by
Eastons, Amos & Anderson to Hawkshaw's design. The
contemporary passage between the South Dock and its
basin - which was 176ft by 55ft - had two pairs of
similar gates, fitted as reverse-sweep. (ref. 375)
Steamships became ever bigger and the lock soon
proved to have been insufficiently enlarged. The South
Dock was, excepting Tilbury, the deepest dock in the
Port in the late nineteenth century, but access was
restricted by the length of its entrance lock. Use of the
South Dock fell markedly after the opening of the rebuilt
Blackwall entrance in 1894. Its berths were too valuable
to be left idle, however, and in 1897 H. F. Donaldson
proposed a cut from the Export Dock as a means of
reviving it. However, Captain Charles Ayerst, a dockmaster, objected that two berths would be destroyed and
that, in any case, the Blackwall entrance was already used
to its limit. He suggested the reconstruction of the South
Dock entrance, to deepen it and provide a uniform
width. Inverted-arched bottoms had become inconvenient
because ships of squarish section reduced the effective
depth of the lock to that measured at the sides. The
question remained unresolved until 1899, when the Joint
Committee Chairman, Charles James Cater Scott, intervened decisively in favour of enlarging the lock. Henry
Charles Baggallay prepared plans, and Charles Hay
Walker & Company, who had recently built docks at
Buenos Aires, carried out the work in 1900–2 for
£54,833. (ref. 376) The lock was made 29ft deep with a squared
concrete bottom, and lengthened from 300ft to 480ft in
mass concrete with granite dressings. The lengthening
amounted to the addition of an 180ft-long inner chamber
in the South Dock Basin, giving long and short locks to
permit the locking of small craft without serious water
loss, following the examples of the Millwall Dock and
Blackwall entrance locks. One of the little-used pairs of
gates in the passage between the South Dock and its
basin was repositioned. (ref. 377)
Once again this was too little too late. Only two years
after the lock reopened the Glen Line moved from the
South Dock to the Royal Albert Dock, as the depth of
water in the lock was insufficient. (ref. 378) Another rebuilding
of the South Dock entrance was a central part of Frederick
Palmer's scheme of 1910 for improving the West India
Docks. His first plan envisaged a wholly new lock, 575ft
long, 80ft wide and 40ft deep, directed up-river across
the Canal Dockyard site. This was revised in 1911 in
favour of a short lock leading to a basin, to admit vessels
650ft long. C. R. S. Kirkpatrick altered the plan in 1914–
17, reverting to a lock directed up-river, 650ft long, 100ft
wide and 45ft deep, but there was no money for the
work. (ref. 379)
Plans to rebuild the South Dock entrance were revived
in 1925 as the central feature of the West India and
Millwall Docks Improvement Scheme. The proposal for
a new lock was abandoned in favour of enlarging the
existing one, which, with new cuts or passages, would
serve the entire West India and Millwall system. Palmer
and F. W. D. Davis recast Kirkpatrick's plans and
proposed a lock 550ft long, which was thought to be
large enough for any shipping likely to navigate so far
upstream. (ref. 380) However, T. & J. Harrison applied for a
berth in the South Dock and, to suit their vessels, Palmer
altered the plans in 1926–7 to make the lock 590ft long.
The building contract went to Sir Robert McAlpine &
Sons, then at work on a PLA lock at Tilbury, and work
commenced in September 1927. (ref. 381)
The three pairs of lock gates were supplied by the
Cleveland Bridge & Engineering Company, of Darlington,
for £48,252. Other contracts went to Carrick & Wardale
for two 5-ton and four 11-ton hydraulic capstans, Glenfield & Kennedy for hydraulic and hand-operated penstocks for the filling culverts, and the East Ferry Road
Engineering Works Company for direct-acting hydraulic
rams for the lock gates. (ref. 382) Large 'Bean' and other bollards
were also fitted. The lock was completed more than a
year ahead of schedule, opening on 5 September 1929 at
a final cost of £627,470 (Plate 46d). (ref. 383)
The lock, 955ft long overall, has a 450ft inner and
140ft outer chamber, is 80ft wide and 35ft deep (fig. 96j).
It followed the slightly earlier and much larger lock at
Tilbury in most of its particulars. The walls and invert
were built of mass concrete, the walls in steel sheet-piled
trenches. The hollow quoins and sills are of granite,
with granite concrete used for other dressings, including
precast coping-blocks. The steel gates, each 45ft 6in. by
38ft and weighing 158 tons, are water-borne with air
chambers for buoyancy, obviating rollers. Steel sheetpiled coffer-dams were used, and timber pierhead jetties
were built from the wing walls, 70ft long to the north,
170ft long to the south, both 25ft wide. The south
pierhead was rebuilt in 1950, and was partially rebuilt
again in 1962 (ref. 384) The water area on the south side of the
west end of the lock was used as a barge berth. (ref. 385)
The lock was repaired in 1959–60 by John Mowlem &
Company, by the removal of the coping and facing wall
east of the middle gates to a depth of about 6ft, and
rebuilding in brick-faced monolithic concrete, reinforced
with a lattice of rails anchored to the main walling. (ref. 386)
Junction Dock
The Junction Dock was built in 1853–5 to link the South
Dock to other parts of the West India Docks. Such a cut
had been desired for many years. In 1819 John Rennie
had put forward a proposal for a locked passage between
the Blackwall Basin and the City Canal. The principal
recommendation for such a cut was that the canal's east
entrance might double as an entrance to the docks,
permitting rebuilding of the troublesome Blackwall
entrance lock. (ref. 387) In 1820 Rennie developed the idea as a
grand proposal for a nine-acre dock south of the Blackwall
Basin with a new river entrance. The estimated cost of
£289,247 was too high to gain approval while the dock
company's charter was under review, and the scheme was
not executed. (ref. 388)
The matter remained unresolved until 1851, when the
dock company was forced into action by the collapse of
the Blackwall entrance north wing wall. (ref. 389) The docks did
not have to close, but they might well have done. James
Meadows Rendel, brought in to advise on the wing wall
repair, suggested building a linking cut from the South
Dock to the Blackwall Basin, and Henry Martin, J. S.
Adams and senior dockmasters concurred. Martin and
Adams prepared plans for a rectangular 'junction dock',
and Rendel designed an irregularly shaped basin capable
of conversion into a new entrance lock. The company's
officers and Money Wigram, a director, thought a new
entrance unnecessary and favoured Martin and Adams's
proposal. Their scheme was less forward-looking than was
Rendel's, but was more practical in terms of immediate
requirements. Rendel revised the plans to suit the dock
officers: a dock 400ft by 340ft, with entrances 50ft wide
and 26ft deep at high water, had to be scaled down to
one 150ft by 320ft, with entrances 45ft wide and 25ft
deep, to reduce the estimate from £103,000 to £65,000.
The plan was further amended to include timber slips
with cranes, to serve adjoining wood-piling grounds,
before it was approved in April 1852. (ref. 390)
Excavation of the Junction Dock by Thomas Brassey
and William McCormick commenced in early 1853, and
progressed slowly, as pumping proved difficult. Rendel
and his Resident Engineer, A. T. Andrews, had great
trouble bringing Brassey's attention to delays. Brassey
(1805–70), the great railway contractor, who was generally
in Paris, was accused of not giving the work the attention
he had promised and, after further exhortations to him
to push the works ahead had failed, Rendel concluded
with exasperation that Brassey had 'compromised himself
as a man of business'. Completion had been projected
for March 1854, but the dock was not open to shipping
until November 1855. The final cost was £82,797. (ref. 391)
The Junction Dock was built with Kentish-rag-faced
concrete footings to brick walls with slightly battered
sides (fig. 96c). The entrance passages were straightsided with inverted-arched bottoms and timber reversesweep gates. Only one granite-faced timber slip was
built. (ref. 392)
The Junction Dock was never much used other than
as berths for exports and timber imports (Plate 50b). (ref. 393)
The rebuilding of the Blackwall entrance for which it
had, in part, been conceived was not carried out until
the 1890s, by which time it was too small for much
shipping. The PLA's early improvement schemes envisaged the entire displacement of the Junction Dock. It
survived, however, with its south entrance filled in 1927–9
for the rebuilding of the South Dock east entrance
lock. The Junction Dock was filled in by the PLA in
1979–80 as part of an agreement for the lease of the site
to Teltscher Brothers Limited. (ref. 394)
The Bellmouth, Export and Millwall Passages
Water communication between the various parts of the
West India Dock system was improved by the Junction
Dock, but only to a limited degree. Palmer's scheme of
1910 proposed a large 'communicating' basin, abandoned
in favour of keeping the South Dock distinct. In 1914
Kirkpatrick revived the idea of opening up the system,
with a plan that included open water at the east ends of
the Import, Export and South Docks, and a passage to the
Millwall Inner Dock. (ref. 395) Financial constraints prevented
action until 1924, when alternative proposals were submitted by Kirkpatrick and D. J. Owen. Palmer and
F. W. D. Davis took over the engineering of the scheme
in 1925. It included three 29ft-deep passages to link the
docks and to ease mobility for the large ships that the
rebuilt South Dock entrance would admit. Kirkpatrick's
cut to link the South Dock and the Millwall Inner Dock
was retained as the Millwall Passage, 480ft long and 80ft
wide. The plans also included a passage, 180ft long and
550ft wide, between the Export and South Docks and
another, 332ft by 80ft, between the Export and Import
Docks, positioned to align with the Millwall Passage.
Palmer suggested that the passage linking the Import
Dock and the Export Dock should have a uniform width
of 300ft, but it was given a 'bellmouth' on its north side,
to admit large ships into the Import Dock while allowing
its south end to be spanned by a bridge. Another of
Palmer's suggestions, that the Middle Cut or Export
Passage be reduced to 350ft wide, was approved. (ref. 396)
The three passages were made part of a large contract
given to Charles Brand & Son in February 1926, with
George Corderoy & Company as quantity surveyors. The
Export Passage was made quickly and opened to shipping
in 1927, to allow the South Dock to be used after
closure of its entrance lock. The Millwall Passage and
the Bellmouth Passage were completed in 1928 (fig.
96i). (ref. 397) The passages have mass-concrete walls, 16ft 6in.
thick at their bases, with granite coping and Portland
stone dressings for the water-depth indicators, 'Bean'
bollards and fairleads. The walls were built in trenches,
40ft deep, before the old quay walls at the Export and
Bellmouth Passages were removed. The Millwall Passage
was excavated in the dry. (ref. 398)
Surviving Structures
In 1994, much of the West India Docks enclosed water
system survives. The Import Dock and Export Dock are
to the north and south of Canary Wharf and, though
apparently reduced in size, they retain most of their brick
walling of 1800–6 under recent decks, and, at the north
quay, behind the 'false' quay of 1912 15. The Blackwall
Basin is still approximately its original size, with secondary quay walls. The Blackwall Entrance Lock is as
rebuilt in 1893–4, though it has recently been permanently dammed. Of the early interconnections, only
that between the Blackwall Basin and the Import Dock
survives, as a passage of 1892 4. The West India Dock
Graving Dock of 1876–8, reconstructed in 1948–9, is
permanently filled, but does still exist. The South Dock
is of 1866–70, as enlarged and altered in 1929–30.
Remarkably, the City Canal west entrance lock of 1803 5
survives, used since 1930 as an inlet for impounding
water. The South Dock East Entrance Lock, repeatedly
rebuilt, is of 1927–9, and the Bellmouth, Export and
Millwall Passages of 1926–8 have all survived.